POWER SECTOR TACKLES ENERGY THEFT AS EFCC INVESTIGATES COLLUSION BY STAFF, CUSTOMERS, METER MANUFACTURERS TO BYPASS IBADAN DISCO’S METERS ·      As Sector Operators report progress in project executions to boost supply : Community connection projects in Magboro completed by NDPHC, currently undergoing testing by IBEDC

Date:

By Adebisi Adeyemi Lagos, Nigeria

 

As Sector Operators report progress in project executions to boost supply : Community connection projects in Magboro completed by NDPHC, currently undergoing testing by IBEDC

  • Katampe 60MVA substation in Abuja restore , 40 MVA mobile substation in Damboa, Borno State commissioned by TCN
  • Makeri to Pankshin 132kV and Okpella lines to be switched on in August, installation of new circuit breaker in Egbin slated for May 19

Efforts to curb the incidence of energy theft in the Nigerian Electricity Supply Industry (NESI) is being intensified with the on going investigation of the collusion by some staff, customers and meter manufacturers to bypass meters under some of the areas covered by the Ibadan Electricity Distribution Company.

This development along with significant progress in on going electricity generation and transmission projects execution across the country were some of the highlights captured in the Communique of the 15th Monthly Meeting of the Power Sector Operators presided over by the Minister of Power Works and Housing, Mr. Babatunde Fashola SAN, at the NIPP Injection Substation, Lamingo, Jos.

According to the Communiqué, ”Ibadan Electricity Distribution Company noted that collusion by some of its staff, customers and meter manufacturers to bypass meters has been reported to Economic and Financial Crimes Commission (EFCC) and is under investigation.”

 

The Niger Delta Power Holding Company (NDPHC) also announced the completion of host community connection projects in Magboro, which is currently undergoing testing by Ibadan Electricity Distribution Company and the progress being made in the community connections in Egbema, Okija, Oronta, Ihiala, and Nnewi in the South-East.

 

On its part, the Transmission Company of Nigeria (TCN) reported that Katampe 60MVA substation in Abuja was restored on April 11, 2017 and the 40 MVA mobile substation in Damboa, Borno State was commissioned on May 7, 2017, while the Makeri to Pankshin 132kV line in Plateau and Okpella line in Edo State were both expected to be switched on in August 2017 adding that the installation of new circuit breaker in Egbin was scheduled for commissioning on May 19, 2017.

 

In the area of customer service, while the Nigerian Electrical Regulatory Company (NERC) announced its intention to reduce the number of days required to access electricity connections in new buildings from an estimated 198 to 30 days through a regulatory Order to be released shortly, Jos Electricity Distribution Plc (JED) reported on complaints on fast reading meters in its coverage areas which were forwarded to the Minister and agreed to resolve the issues to the satisfaction of consumers.

READ ALSO  COVID-19: SANWO-OLU COMMISSIONS ARMOURED SHIELD ISOLATION CENTRE IN LAGOS

 

Hope of a boost in liquidity in the sector rose also as the Nigerian Bulk Electricity Trader (NBET) reported on international customer payments, stating that the Republic of Niger (NIGELEC) and Republic of Benin (CEB) had made payments for power of $159,773, 116.61, with a combined balance still outstanding of $92,315,986.20, adding that payments had been duly remitted to the Generating Companies and Service Providers who, it said, had provided the generation and transmission services.

 

In the same vein, the Senior Special Assistant to the President on Power, and Managing Director of the Rural Electrification Agency (REA) reiterated the commitment of the Federal Government to paying verifiable power debts, and announced the completion of physical verification of the top 100 MDA locations in Abuja Electricity Distribution Company (AEDC) with plans to visit Eko and Ikeja DisCos for physical verification as a prelude to payment.

 

In terms of payment performance for service provision among the DisCos, the Market Operator reported that Eko DisCo was the best performer at 89 per cent while Kaduna DisCo recorded the worst performance at 13 per cent. And in terms of registration as power market participants amongst DisCos, Abuja Electricity Company, APL Electricity Company, Kaduna Electricity Company and Geometric Power have not completed registration while amongst GenCos, Delta Power, Okpai, Omoku and NIPP plants are yet to complete registration.

 

In the Communiqué, the operators, who noted that the Monthly Meeting serves as forum for Providing an opportunity to inspect electricity assets and for power sector decision makers to take critical decisions in unison to move the sector forward as well as providing correct sector information to the public noted that while the first and second objectives had been largely achieved, the third had not been achieved.

READ ALSO  Some forces working to frustrate PIB – Senate President

 

Blaming it on the inaccurate information often disseminated by the Association of Nigerian Electricity Distributors (ANED) regarding the plan to escrow accounts earlier agreed by the DisCos themselves as a condition before accessing low priced loans from the Federal Government, the Communiqué averred that by failing to mention the fact that the conditions of the loans were not mandatory, but were terms of the credit facility, information advertised by ANED were misleading.

 

Additionally, the Communiqué stated, lack of corporate governance displayed by some DisCos, evidenced by failing to provide audited accounts, improved services and urgent response to customer complaints, meters and network investment had shown inconsistencies in DisCo statements, pointing out that the Federal Government had expended income to verify any claims accurately made against them, to the knowledge of the DisCos.

 

The meeting also noted that the failure of Distribution Companies to remit payment as owed to NBET led to the approval by the Federal Government of Nigeria of N701billion Payment Assurance Guarantee to Generating Companies, to fill the payment gap.

 

Expressing regrets over the electrical accident which occurred on April 20, 2017 in Calabar, Cross River State for which it observed a moment of silence, the Meeting reiterated the need to prioritize safety regulations and emphasized the need for the support of the sector regulators.

 

In order to avert similar incident in the future, the Meeting announced, for the information of the public, applicable regulations for setback saying for 330kV lines a total of 50 metres setback was required consisting of 25metres on each side from the centre while 132kV and 33kV lines required a total 30 metres (15 m on each side) and a total 3.5 metres setback respectively.

 

For 11KV lines, a total 3 metres setback is required while 41kV lines require 1.5 metres setback and underground cables are to be buried at least 3 metres below the ground surface, the Meeting said while also agreeing that buildings and structures built beneath ‘high tension’ power lines should be disconnected from power supply systems as already issued by NEMSA to DisCos for reasons of safety.

 

Enjoining the public to halt the practice of illegally constructing structures beneath and illegally connecting to power lines, the Meeting said it would encourage prioritisation of investment in education and communication on electrical safety measures through the creation of a task force within the sector, adding that it would work with state governors to reduce accidents as a course of action.

READ ALSO  GOVERNOR WIKE ACCUSES FORMER GOVERNOR OF FORMING NEW CULT GROUP

 

According to the Communiqué, the Governor of Plateau State, Mr. Simon Lalong, highlighted the work being done in various areas of Plateau State to supply power using solar, wind and other renewable resources saying they were complimentary to the Federal Government’s projects.

 

The Governor acknowledged, with gratitude, the importance of the Federal Government projects in the state, particularly the 132kV line from Makeri to Pankshin and their potential to boost tourism, agriculture and power to rural communities, as well as various rural electrification projects being undertaken by the Rural Electrification Agency.

 

The Meeting, chaired by the Minister of Power, Works and Housing, Mr Babatunde Fashola SAN, was hosted by Jos Electricity Distribution Plc at NIPP Injection Substation, Lamingo, Jos and had in attendance the Plateau State Governor, Hon. Simon Lalong as well as the Chairman of Jos Electricity Distribution Plc, Alh. Yayale Ahmed.

 

Focused, as usual, on identifying, discussing, and finding practical solutions to critical issues facing the Nigerian Electricity Supply Industry, the Meeting also had in attendance Power Sector Operators who were fully represented at the highest executive management levels, including Commissioners of the Nigerian Electricity Regulatory Commission (NERC).

 

Also in attendance were the Managing Directors and CEOs of Generating Companies (GenCos), Distribution Companies (DisCos), and the Transmission Company of Nigeria (TCN), Gas Companies (GasCos) and other government agencies such as the Niger Delta Power Holding Company (NDPHC) and the Nigerian Bulk Electricity Trader (NBET).

 

Others were the Managing Director and CEOs of the Nigerian Electricity Liability Management Company (NELMCO) and Nigerian Electricity Management Services Agency (NEMSA) responsible for the regulation and development of the electricity industry as well as the Nigerian National Petroleum Company (NNPC) and the Central Bank of Nigeria (CBN).

 

spot_img

Share post:

Subscribe

Popular

More like this
Related

LAGOS TO COLLABORATE WITH META PLATFORM TO DEEPEN DIGITAL SPACE

LAGOS STATE GOVERNMENT OFFICE OF THE SPECIAL ADVISER TO THE...

Kaduna Gov meets President Tinubu over kidnapped Kuriga School Children

Kaduna State Governor Uba Sani has continued to strategize...

GOV FUBARA, CJN, OTHERS HONOUR JUSTICE ODILI AT BoB SEND FORTH

OV FUBARA, CJN, OTHERS HONOUR JUSTICE ODILI AT BoB...

Olatunji released, as IPI, NGE, NUJ urge Tinubu to punish Generals Musa, Undiandeye

Let’s Protect Free Press, Let’s Protect Our Democracy against...